Create dependencies by connecting follower and predecessor cards to initiatives as a way to organize your workflow. Please note that your company's instance of Wave may vary from the examples below.

 

Step-by-step instructions

1. Open the initiative card that will have time dependencies. Select Predecessors (or Followers) and click on + ADD PREDECESSOR (or + ADD FOLLOWER).

Dependencies - Add.gif

 

2. In the pop-up search bar, enter the number of the initiative (or action, milestone, activity, etc.) or keyword associated with the initiative (or action, milestone, activity, etc.) you want to add as a predecessor (or follower). Select the initiative and it will be added as a predecessor (or follower).

Dependencies - Add 2.gif